Connect with us

Current Affairs

Kunzvi Dam Nears Completion in Final Phase

Published

on

By Itai Mazire

Kunzvi Dam construction is rapidly advancing, with the project currently at an impressive 67 percent completion, the Zimbabwe National Water Authority (ZINWA) has revealed.

Head of Corporate Communications and Marketing, Mrs. Marjorie Munyonga, said the project is on course to impound water in the forthcoming rainy season.

“Ongoing works at the dam site include the placing of core and fill material, hauling of sand and blasted stones, as well as steel fixing on the outlet works.

“A cumulative total of 28,390 cubic metres of riprap has been placed on the left bank together with a cumulative 635,620 cubic metres of fill material.

“Also in progress on the left bank is chimney sand placement, where a total of 96.5 cubic metres of sand has since been placed.

“On the riverbed section, fill placement is also underway, with a total of 10,380 cubic metres having been placed this week, bringing the cumulative total of fill placed on the riverbed to 131,720 cubic metres.

“This week, 6,200 cubic metres of core material was placed on the riverbed, bringing the total tally of core material placed on the riverbed to 191,560 cubic metres,” said Mrs. Munyonga.

Once completed, the project is expected to help ease water challenges in Harare by providing water for the capital’s eastern suburbs.

Currently on site is the construction of a 48-kilometre pipeline, which will channel raw water from Kunzvi to a treatment plant set to be developed at Donnybrook in eastern Harare. Once complete, it will convey up to 240 megalitres of water daily, significantly easing the capital’s deficit, with current daily supplies averaging 400 megalitres against a demand of about 800 megalitres.

The pipeline is a central component of the Harare East Water Augmentation Project, which had stalled for years largely due to financial constraints. It is being implemented by local contractor Redan Bulk under a USD 52 million tender awarded by ZINWA.

Mrs. Munyonga said preliminary indications on the ground show that the project will be completed by year-end.

“On the right bank, backfilling of the D-Tunnel is in progress, and 2,930 cubic metres of backfill material has been placed. Steel fixing is also being done on the intake tower, where formwork placing is underway.

“As for core material placement on the right bank, 66,990 cubic metres have been placed, together with 45,530 cubic metres of fill material and 140 cubic metres of riprap.

“Slope trimming is progressing quite well on the right bank, where 90 metres have been trimmed upstream and a further 12 metres downstream.
“Excavations of the spillway are now at an advanced stage, with 20,350 cubic metres having been excavated for the gate and 1,740 cubic metres of backfill material placed.

“Shuttering of the spillway substructure is also being carried out.
“Sand and quarry stone hauling is being undertaken as well, and 1,830 cubic metres of sand have been stockpiled from the Nyagui sand source,” said Mrs. Munyonga.

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Current Affairs

Rainy Season Begins with Mixed Feelings

Published

on

Rainy Season Begins with Mixed Feelings
Residents prepare for the rainy season as clouds gather over Zimbabwe. (Pic: Credit Internet)

After a delayed start to the 2025-2026 rainy season, widespread downpours swept across Zimbabwe this week, delivering over 50 mm in multiple districts and signalling the onset of planting under the Pfumvudza/Intwasa program.

The Meteorological Services Department (MSD) reported a moisture-laden system from Botswana and the southeast blanketing Matabeleland North and South, Bulawayo, Midlands, Manicaland, Harare, and all Mashonaland provinces.

Lightning and strong winds accompanied the storms. Farmers in Mashonaland Central, Masvingo, and Midlands have begun land preparation, collecting seeds via Agritex offices.

 

The MSD forecasts normal to above-normal rainfall from November to January under neutral ENSO and negative Indian Ocean Dipole conditions.

“This is prime time for early-maturing crops and moisture conservation,” the MSD said.

“Avoid flood-prone fields and follow regional advisories,” a Zimbabwe Farmers Union official said.

In cities, clogged drains caused road flooding and power cuts in Harare, Chitungwiza, and Bulawayo. Mbare and Kuwadzana residents reported sewer overflows.

The Civil Protection Department activated provincial teams and urged schools and clinics in vulnerable areas to update evacuation plans.

Civil society groups pushed for community early-warning systems and better data sharing to address past coordination failures.

Continue Reading

Current Affairs

President Mnangagwa Orders By-Election for Nkulumane Seat

Published

on

President Mnangagwa Orders By-Election for Nkulumane Seat
President Emmerson Mnangagwa signs Proclamation 6 of 2025 in Harare, ordering a by-election for Nkulumane constituency following the death of Zanu-PF MP Desire Moyo
President Emmerson Mnangagwa on Thursday proclaimed a by-election to fill the vacant Nkulumane National Assembly seat following the death of incumbent Member of Parliament Desire Moyo last month.
Moyo, a Zanu-PF legislator representing the Bulawayo constituency, died on October 10, 2025, after a short illness.
The Speaker of Parliament formally notified the President of the vacancy on October 31, triggering the constitutional process for a replacement.
Under Statutory Instrument 169A of 2025 and Proclamation 6 of 2025, President Mnangagwa set November 20 as nomination day at the Magistrates’ Court in Bulawayo and December 20 as polling day if a contest occurs.
The proclamation cites section 39(2) of the Electoral Act, which mandates the President to call a by-election within 90 days of being informed of a parliamentary vacancy.
Nkulumane, a traditionally opposition-leaning urban seat, has been held by CCC since the 2023 harmonised elections.
Continue Reading

Current Affairs

Government Confirms Restricted Access to Mbuya Nehanda Statue After Vandalism Attempts

Published

on

By

The Government has acknowledged that the Mbuya Nehanda statue in Harare’s central business district was closed off to the public after multiple acts of vandalism were attempted.

Permanent Secretary in the Ministry of Information, Publicity and Broadcasting Services, Nick Mangwana, confirmed that authorities decided to limit public access to the site to prevent further damage to the monument.

“The monument was originally open to the public. However, due to increased visitor traffic and several attempts to damage or topple it, the area had to be secured,” Mangwana explained in a post on X (formerly Twitter).

He further revealed that plans are now underway to reopen the site safely.

“The Government is developing a new access framework that will allow public viewing while ensuring the statue’s protection. The President has directed that this process be expedited, and we sincerely apologize for the inconvenience caused by the closure,” he added.

The Mbuya Nehanda statue, which was officially unveiled by President Emmerson Mnangagwa in 2021, was constructed at significant cost and is located at the intersection of Samora Machel Avenue and Julius Nyerere Way. Since its unveiling, the monument has remained under constant police guard and out of reach to ordinary citizens.

Mangwana’s remarks come after a recent outcry sparked by international travel vlogger Davud Akhundzada, who was denied access to the monument during his visit to Harare — a move that critics said undermined tourism promotion efforts.

In response to the backlash, the Ministry of Tourism and Hospitality Industry issued a statement clarifying that the statue falls under the authority of the Ministry of Home Affairs and Cultural Heritage.

“The Mbuya Nehanda Statue is a National Heritage Monument managed by the Ministry of Home Affairs and Cultural Heritage. It represents Zimbabwe’s liberation heritage and national identity,” the Ministry said.

It added that access to certain parts of the site is restricted for preservation, safety, and security purposes.

The Tourism Ministry also noted that it is collaborating with the Ministry of Home Affairs under the Whole-of-Government Approach to improve visitor experiences at heritage sites.

“As part of this initiative, tourism officers will be deployed at key cultural and heritage monuments to facilitate guided, informative, and friendly access for visitors — ensuring a positive tourism experience while preserving our national heritage,” the statement concluded.

Continue Reading

Trending